Skip to content Skip to footer

Canisteo-Greenwood Capital Project Update

November 10th, 2014

CANISTEO, NY – At last night’s monthly Canisteo-Greenwood board of education meeting representatives from Labella Associates updated the board on progress of the $6.8 million capital project currently under way on the school district buildings.

Representatives from Labella report that things are financially on target, with $3.9 million spent and $2.9 million balance remaining, and 70% of the work completed.

With the gymnasium mostly completed, the only major work left is the kitchen/cafeteria interior and exterior. A spokesperson from Cabella told the board that the project will not be finished in middle January, as anticipated but will be pushed back at least three weeks mostly due to the unforeseen work performed on the gym roof.


Office

WLEA/WCKR
5942 County Route 64
Hornell, New York, 14843

607-324-1480
Fax: 607-324-5415

Links

newsroom@wlea.net

To Advertise On Wlea:

prodo@wysl1040.com

585-346-3000

Get in Touch
WLEA.NET © 2025. All Rights Reserved.
Social Share Buttons and Icons powered by Ultimatelysocial