April 17, 2026
FROM CANISTEO-GREENWOOD SUPERINTENDENT TOM CROOK: Progress Update: Project continues to progress nicely. The auditorium scaffolding has been removed, the ceiling and catwalk look great, and the stage rigging is being installed. The next four elementary classroooms are complete (other than punch list items) and have been turned back over to the school district. The new playground equipment is on site and installation will begin as soon as it dries out more. Bus garage work has begun with the installation of the generator, the overhead doors, and the HVAC renovations. Finally, the main competition gym in the elementary school has been taken over and demolition has begun.
Regularly scheduled job coordination meetings continue between the trades and ongoing leadership level meetings with the District leadership team, Hunt EAS, LeChase, and Donegan Financial Advisors continue as well.
Each area of construction contains a more specific update below:
Auditorium –The scaffolding has been removed and the drywall work is nearly complete. Rigging equipment is being installed. KI seating has been on site for final measurements for the seats. The seats are being manufactured and should be on site in early June.
Elementary Competition Gymnasium- The elementary gymnasium was taken over during spring break. The contractors did an amazing job getting the major demolition work completed while students were not on campus. The bleachers and backboards were disassembled and removed, and the existing wood flooring was removed in sections with proper exhaust and ventilation provided to safely do the job while protecting the adjacent hallways of any dust issues. Some mortar work is now being completed on the walls, and the concrete is being prepared for the new wood floors. Simultaneously, electricians are working on running new conduit and pulling wires. Painters will be in the gym in late April. The new wood floors will be in site in early May to be properly acclimated to the environment, followed by installation. This was a great start to the gym project!
Athletic Facility/Turf Field – The punch list work is complete in the concession stand bathrooms. The exterior FRP doors are still delayed from the manufacturer and will be installed as they arrive on campus in May. This is the only remaining item for the concession stand. Ball nets were installed at the stadium and minor punch list items are being completed as well.
Elementary Playground- As the warmer weather finally arrives and the ground dries up, the elementary playground will install the new foundations for the new equipment. The new equipment is secured on site. All underground drainage infrastructure was completed last fall. If the weather cooperates, this will be completed and open to students before the end of the school year.
Elementary Entrance/Office and Classrooms – Punch list items in the main office are nearly complete. Wood ceiling baffles were completed in the main entrance area over spring break.
Electrical work continues at the bus garage. Generator has been installed. Overhead doors at the bus garage will be installed this spring/summer as well.
The construction team continues to review the milestone construction schedule weekly to avoid any delays and to plan for installation recovery time of any delayed items. Once again, this summer is going to be very active again as the elementary competition gymnasium and the cafeteria go under anticipated heavy construction.
Once again, a huge thank you to the district leadership team for providing creatively safe options for the project to be phased while school is in session. The district has established a section of website dedicated to the work on the Capital Project. Communication with the staff, students, and community is key to a successful project!